Preparation for mill upgrades

Repeka Nasiko
Saturday, May 17, 2014

PREPARATION works for the next harvesting season in the Labasa sugar mill has entered the final stages, says Fiji Sugar Corporation chairman Abdul Khan.

Mr Khan said preparation works at the mill and the upgrade of the railway system in the North were expected to end by mid-June.

"All the lines are undergoing maintenance of some nature with the major maintenance being carried out on the Wainikoro line," he said.

The Nagigi line was among upgraded railway lines.

Mill manager Christopher Karia said upgrade works would also include the relaying of tramlines.





Fiji Times Front Page Thumbnail

Kaila Front Page ThumbnailFiji Times & Kaila Frontpage PDF Downloads

Use the free Acrobat Reader to view.

Today's Most Read Stories

  1. Old market to turn into live fish shop
  2. FRCA terminates officers
  3. Project a success
  4. New-look bus station plans
  5. Spotlight on shipping company
  6. Bus operators clarify student fares
  7. $18m arrears
  8. Four in custody
  9. School to provide the best
  10. PAC seeks answers

Top Stories this Week

  1. Breaking the silence Wednesday (21 Jan)
  2. No payout for police Wednesday (21 Jan)
  3. 'No money' in 2004 Wednesday (21 Jan)
  4. Opposition challenges PM to walk the talk Friday (23 Jan)
  5. Disappointment at late posting of graduate teachers Wednesday (21 Jan)
  6. Ten days time Thursday (22 Jan)
  7. Ba retains title Monday (26 Jan)
  8. Things you didn't know about Kuridrani Monday (26 Jan)
  9. PM's apology to Fiji Saturday (24 Jan)
  10. Best for our players Wednesday (21 Jan)